解決國4匝道車流堵塞 后豐大橋下游側新建引道年底完工通車

《圖說》立委<a class="link " href="https://tw.news.yahoo.com/tag/楊瓊瓔" data-i13n="sec:content-canvas;subsec:anchor_text;elm:context_link" data-ylk="slk:楊瓊瓔;sec:content-canvas;subsec:anchor_text;elm:context_link;itc:0">楊瓊瓔</a>及市議員<a class="link " href="https://tw.news.yahoo.com/tag/羅永珍" data-i13n="sec:content-canvas;subsec:anchor_text;elm:context_link" data-ylk="slk:羅永珍;sec:content-canvas;subsec:anchor_text;elm:context_link;itc:0">羅永珍</a>、<a class="link " href="https://tw.news.yahoo.com/tag/陳本添" data-i13n="sec:content-canvas;subsec:anchor_text;elm:context_link" data-ylk="slk:陳本添;sec:content-canvas;subsec:anchor_text;elm:context_link;itc:0">陳本添</a>推動增設<a class="link " href="https://tw.news.yahoo.com/tag/后豐大橋" data-i13n="sec:content-canvas;subsec:anchor_text;elm:context_link" data-ylk="slk:后豐大橋;sec:content-canvas;subsec:anchor_text;elm:context_link;itc:0">后豐大橋</a>下游側引道銜接<a class="link " href="https://tw.news.yahoo.com/tag/堤南路" data-i13n="sec:content-canvas;subsec:anchor_text;elm:context_link" data-ylk="slk:堤南路;sec:content-canvas;subsec:anchor_text;elm:context_link;itc:0">堤南路</a>。

【民眾網諸葛志一台中報導】為解決后豐大橋與國4匝道車流堵塞問題,立委楊瓊瓔及市議員羅永珍、陳本添推動增設后豐大橋下游側引道銜接堤南路,預計可省下15分鐘車程,中央、地方投入近9856萬元經費,預定農曆年後動工,力拚年底年完工通車。

楊瓊瓔與市議員羅永珍、陳本添23日召開「台13線后豐大橋下游側橋面新增引道銜接堤南路」協調會。建設局說明,后豐大橋新增引道工程,在下游側新增35.7公尺長引橋,新闢1800公尺長的路堤,銜接堤南路通往豐洲科技工業園區,堤南路既有路面老舊龜裂,一併修整袍鋪900公尺。引道工程總經費9856萬元,感謝楊委員爭取中央補助8082萬元,地方自籌1774萬元,已完成發包程序,目前正辦理河川公地施工核准,預定農曆年後開工。

引道工程涉及河川公地,第三河川分署長張稚煇表示,已收到建設局申請書件,部分格式、資料尚須補正,因涉及署內三單位審核,建議申請單位儘速補正。

羅永珍指出,涉及私有土地徵收,引道工程只能單向西接堤南路,而堤南路無法東接后豐大橋,盼未來雙向通行。陳本添提醒,未來完工,后豐大橋指示牌面要做好規畫,妥善宣導。

楊瓊瓔表示,爭取中央補助不容易,尤其須在今年年底期限內完成,未來完工通車後,可望縮短15分鐘車程,減少尖峰時刻交通壅塞,降低交通事故發生,促進豐洲一、二期工業園區發展。